CertainTeed – Asphalt Unloading Station

Share Project:

Corval Group was prime contractor for CertainTeed’s new asphalt unloading and processing expansion. The purpose of the project was to install mechanical systems to allow for asphalt to be unloaded from rail cars or trucks, processed and stored at the existing facility. Up to 1 million gallons of asphalt can be stored until it is ready to be moved into the existing facility and used for roof shingle production. The scope of work included installation of piping, pumps, specialties, and structural steel. Also included were several critical lifts for tanks and equipment. Shop fabrication capabilities were utilized to perform over half of the required welds offsite in Corval fabrication facilities. The main challenge of the project was to maintain the schedule through tough winter conditions as over 95% of work performed was outside.

Construction Facts:
• 30,000 Man Hours Self-Performed
• Project Completed on Time for Start-up
• Zero Recordable Injuries
• Managed Over $900,000 in Subcontractors
• Zero Pipe Weld Quality Issues

Industry

Manufacturing

Project Duration

10 Months

Location

Shakopee, MN

Want to know more? Contact us.

Similar Projects

PURIS Proteins, LLC – New Production Facility

Corval Group served as the general contractor for PURIS Proteins LLC’s…

Louis Dreyfus – Crush Facility

LDM Foods selected Corval Group and our joint venture partner as…

HaF Jabil Cryogenic Milling

Corval was the design-Build Contractor for HaF Equipment and installed new…